Lane closures on Belmont Ridge Road between Rt. 7 and Riverside Parkway will take place throughout June and into part of July, Loudoun County's government announced Friday.

The closures, which begin Monday, are necessary for utility relocation work by Washington Gas as part of the Rt. 7/Belmont Ridge Road interchange construction project. They're scheduled to occur in three phases over a six-week period.

The phases are as follows:

• Phase 1, June 1 to 11: One southbound lane of Belmont Ridge, between Promenade Drive and Rt. 7, will be closed with the other southbound lane remaining open. Both northbound lanes will remain open.

• Phase 2, June 12 to 30: One southbound lane and one northbound lane, between Promenade and Rt. 7, will be closed with one southbound and one northbound lane staying open.

• Phase 3, July 1 to 15: One northbound lane between Rt. 7 and Promenade will be closed with the other northbound lane remaining open.

Signs will point out the lane closures for drivers, but questions about the project may be directed to Loudoun County's construction manager, Javier Castro, at .(JavaScript must be enabled to view this email address), or at 571-258-3876.

Back to the Leesburg Today archives

As Seen IN PRINT
The Loudoun Times-Mirror

is an interactive, digital replica
of the printed newspaper.
Click here for all e-editions.
Email UPDATES